In the case of the recent assessment by Shorebreak, ECS and AD EED became aware of testing after it began. After becoming aware of the ongoing assessment the Control System (Software) Working Group (CSWG) engaged with SLAC Cybersecurity to identify especially sensitive networks which would be off-limits during these tests, as well as networks would which would require advance notice from Shorebreak before they began their tests so we could inform operations and prepare to recover systems. Greg White helped to ensure the SLAC Cybersecurity and relevant control system experts were able to meet and coordinate and raised awareness of these activities. McCullough, Mark was an excellent point of contact from SLAC IT and patiently helped us find a workable path towards preparation for the DOE assessment and preventing excessive disruption.

...