Margaret Ghaly 

MEC-U

Mitchell Cabral 

LBTS

Jama

FAC

...

MEC-U Controls has slowly begun ramping up in March and April, and we look forward to continue the trend as we shift focus to laser beam transport controls and infrastructure design. Some notable MEC-U topics from the past couple months can be found below. 

Rack Estimates: WIP

Estimated control rack and power quantities for base scope and full scope. Looking forward to meeting with various rack vendors. Visits with Rittal and Steven Engineering in May. 

NNSA and DMPL: WIP

Explain what NNSA is and what DMPL is. How is this different from base MECU scope. Controls giving cost estimate for additional scope. 

FAC Review: WIP

The Facility Advisory Committee Review is not a critical path review, but is an opportunity for each subsystem to present their progress, designs, challenges to experienced personnel who have background in similar laser facilities and projects. 

Talk about charge question.

Organizing deliverable list

SQAP

Overall Architecture

Jira: WIP

We are currently organizing ECS and SLAC CosyLab work through Jira and an MEC-U Kanban board. So far, the board has proven to be effective at increasing visibility of the tasks to be completed at the SLAC Controls Level. Each tasks is organized under an epic, and (most) epics correspond to project activities within P6. 

Image Added

pcds_conda

Zachary L Lentz 

...