...
The HE Controls team have presented their preliminary design for 4 out for the 7 L5 WBS: XPP instrument controls, MFX instrument controls, FEE and XRT area and Common components controls design. Pending the review report, the team is ready to start Final designs. Preliminary design activities for the other areas are on track with good engagement from the team. Activities for 3B reviews and drilldowns preparationsare in progress.
Excerpt Include | ||||
---|---|---|---|---|
|
The latest news on the project is that we have a concept demo up and running. We still need to find some bandwidth to polish the frontend, and then we'll be ready for a release. Aiming for early November.
...