L2HE Project Roles and assignment table can be found here.

...

MEC-U update

Rack allocations

Other controls requirements

LLE+LLNL Onsite Visit

The Rochester and Livermore team came to SLAC on March 22nd and 23rd to learn more about MEC operations and collaborate in person on the project. This was the first time all three partner labs met in person to work on MEC-U. The controls breakout session reviewed the operations and the high-level supervisory control software of the Omega laser facility. We also learned more details about the mechatronics, industrial and timing system controls of the LLE system. 

Hutch Python Update

Hutch python's conda environment was updated to pcds-5.3.1 near the start of April

...