[Tentative proposal]  This power outage will affect substations #7 (next to bldg 50) and #8 (located on the 4th floor of bldg 50).  All of bldg 50 will be without normal power.  The facilities (F&O) group plan to do their maintenance during the 4-day period starting 26 Dec 2019.  However, the outage will start earlier due to lack of staff during the holiday shutdown.  Minimally, it is expected that all H.A. (High Availability) and experiment-critical equipment will be powered throughout the 16+ days of the holiday shutdown.  This page captures what Fermi will need to maintain a minimal data processing effort running during the outage.

 

Note

Note that the ability to perform general science analysis at SLAC by the LAT collaboration will be seriously hindered by this outage due to the fact that much of the batch farm will be unavailable.

...