  • Tim discussed upcoming DOE review on January 18. There is a review page on confluence with preliminary agenda and charge. We discussed who will give the analysis talk. Matt will not be available, Nathan agreed to give the talk.  
  • update on hodoscope (Rafo):
Gluing tests started, so far fiber gluing is going well. After few tries and getting help Hakob, some fibers have been successfully glued. Gluing of aluminized Mylar has been tested as well. Was not clear if scintillator weight is enough to keep minimum amount of glue under the mylar and have a thin uniform layer. Proposal was to add some pressure to keep glue thickness to a minimum.
Next, tests with gluing of fibers into PMT adapter will be done. Plan is to complete all tests before holidays.

...