Tony and Heather need to provide the ability for Gleam to start up Wired just as we currently do for FRED.
Addendum - Other Computing Issues
- ownership of TriggerAlg
- Martin will cede stewardship shortly. There will be a meeting of interested parties on Tuesday (July 15).
- recon seems very slow!
- Tom & Warren are seeing 2.5-3 Hz when reconstructing data runs. Ground muons used to be ~15 Hz. What's up?
- need to keep track of disk resources
- L1Proc seems to be munching xrootd disk at 2-3x the budgeted rate. Probably will recoup the "extra" when we purge superseded L1Proc file versions.
- We need to develop tools to keep an eye on xrootd and Oracle space used.