Deliverable | Complete Date | Responsible | Blockers/Issues |
---|
Write eTraveler assembly and test procedures for Camera Cryostat including refrigeration system. | 11/30/16 | Mark/Robert | |
eTraveler standards, conventions,
best practices documentation. All Camera
subsystems must use | 5/16/16 | Mark/Robert | Standards complete, project to announce and socialize.
|
Write eTraveler procedures for CR wavefront sensor receipt, verification and shipment to SLAC | 6/10/16 | Mark | Input from Camera QA
|
eTraveler procedure for mechanical
assembly of raft electronics boards
(attach coldbars and FPGA heat sink) | Done 5/4/16
| Robert | |
eTraveler procedure for raft electronics
board initial testing (bring up board and
load firmware. Prep for TS-REB testing) | Complete 5/23
| Robert | |
Meet with Camera on what RGA snapshots to post for REB boards | 5/26 | Mark | |
eTraveler procedure for posting RGA
results | Complete TBD | Mark/Robert | Coordination with Mark Bostic at SLAC for posting RGA
results
|