DeliverableComplete DateResponsibleBlockers/Issues
eTraveler standards, conventions,
best practices documentation. All Camera
subsystems must use
5/16/15Mark/Robert
  • (minus) Consensus from Camera project on core standards
eTraveler procedure for mechanical
assembly of raft electronics boards
(attach coldbars and FPGA heat sink)

Done 5/4/16

Robert 
eTraveler procedure for raft electronics
board initial testing (bring up board and
load firmware. Prep for TS-REB testing)

Complete 5/23

Robert 
Meet with Camera on what RGA snapshots to post for REB boards5/13Mark 
eTraveler procedure for posting RGA
results
Complete TBDMark/Robert

Coordination with Mark Bostic at SLAC for posting RGA
results

Medium/long term projects/deliverables

DeliverableComplete DateResponsibleBlockers/Issues
Write demo eTraveler procedures to show Walt Innes
how eTraveler can be used to monitor and control
auxiliary electronics inventory
Done 4/20/16Robert 
With Walt Innes, plan assembly sequence
and eTraveler procedures for ~500
commercial auxiliary electronics parts

Complete TBD
(Ongoing)

Robert 
Write eTraveler procedures for inventory control
of commercial auxiliary electronics parts
6/15Mark/Robert 
Write eTraveler procedures for testing of auxiliary
electronics assemblies as needed (e.g. Camera
protection system)

Complete TBD

Robert 
Consult with SLAC Camera subsystems (Cryo, CBM,
Shutter, I&T) on assembly sequences, scope and "load balancing"
for writing eTraveler procedures
6/15Mark/Robert 
Plan for Camera operations & maintenance
documentation, relationship to eTraveler
7/15Mark/Robert
  • Project decision on how suitable eT is
    for operations and maintenance

...

DeliverableComplete DateResponsibleBlockers/issues
ePix100A detector data sheet5/13Mark 
ePix100A installation guide5/13Mark 
ePix100A detector ops/api guide5/13MarkNeed to know if assembled detector can/will be
pre-calibrated (ASIC calibration) and a config database
delivered 

TID-AIR General Work (??? FTE)

...