Deliverable | Complete Date | Responsible | Blockers/Issues |
---|---|---|---|
eTraveler standards, conventions, best practices documentation. All Camera subsystems must use | 4/27/15 | Mark/Robert |
|
eTraveler procedure for mechanical assembly of raft electronics boards (attach coldbars and FPGA heat sink) | Done 5/4/16 | Robert | |
eTraveler procedure for raft electronics board initial testing (bring up board and load firmware. Prep for functional TS-REB testing) | Complete 5/23 | Robert | |
eTraveler procedure for posting RGA results | Complete TBD | Mark/Robert | Coordination with Mark Bostic at SLAC for posting RGA |
Done 4/20
Deliverable | Complete Date | Responsible | Blockers/Issues | |
---|---|---|---|---|
Write demo eTraveler procedures to show Walt Innes how eTraveler can be used to monitor and control aux elex inventory | Robert | Done 4/20/16 | Robert | |
With Walt Innes, plan assembly sequence and eTraveler procedures for ~500 commercial electronic parts | Complete TBD | Robert | ||
Write eTraveler procedures for inventory control of commercial elx parts | 6/15 | Robert/Mark | ||
Write eTraveler procedures for testing of elx assemblies as needed (e.g. Camera protection system) | Complete TBD | Robert | ||
Consult with SLAC Camera subsystems (Cryo, CBM, Shutter, I&T) on assembly sequences, scope and "load balancing" for writing eTraveler procedures | 6/15 | Mark/Robert | ||
Plan for Camera operations & maintenance documentation, relationship to eTraveler | 7/15 | Mark/Robert |
|
...