LSST Camera (1.8 FTE)

LSSTCAM charge numbers:16714-B2121, 10139-B2019

Other upcoming tasks/issues coordinated with Nadine Kurita for LSST Camera can be found here Camera Documentation Planning.

Short term projects/deliverables

DeliverableComplete DateResponsibleBlockers/Issues
eTraveler standards, conventions,
best practices documentation. All Camera
subsystems must use.
4/27/15Mark/Robert
  • (minus) Consensus from Camera project on core standards
eTraveler procedures for
raft electronics boards

???
(~5 days effort left,
waiting on BNL)

Robert
  • (minus) Final assembly process details from BNL
  • Coordination with Mark Bostic at SLAC for posting RGA
    results

Medium/long term projects/deliverables

DeliverableComplete DateResponsibleBlockers/Issues
With Walt Innes, plan assembly sequence
and eTraveler procedures for ~500
commercial electronic parts
5/15Robert 
Write eTraveler procedures for commercial elx parts6/15Robert/Mark 
Consult with SLAC Camera subsystems (Cryo, CBM,
Shutter, I&T) on assembly sequences, scope and "load balancing"
for writing eTraveler procedures
6/15Mark/Robert 
Plan for Camera operations & maintenance
documentation, relationship to eTraveler
7/15Mark/Robert
  • Project decision on how suitable eT is
    for operations and maintenance

Recurring projects/deliverables

DeliverableComplete DateResponsible
3 monthly reportsMonthly 15th, 31stRobert
Camera subsystem FDR, MRR site and document prepRoughly monthlyMark
Camera document control:
doc mgmt, prep, routing, release
(As needed, currently
4-10 hours per week)
Mark

LCLS-II, LCLS (0.1 FTE)

Charge numbers:13877-T2101

Short term projects/deliverables

DeliverableComplete DateResponsibleBlockers/Issues
Finish release of 0266 ICD4/27Mark
  • Matt Boyes back 4/18. He will guide the doc out.
Finish release of Platform ICD4/20Mark
  • Out for approval according to Matt
Finish release of Timing ICD5/4Mark
  • Talk to Matt Weaver and Boyes on some scope still
    floating around
Finish release of HPS FRSs5/11Mark
  • Get blessing from Matt Boyes on outline/contents
Finish release of HPS ESDs5/11Mark
  • Get blessing from Matt Boyes on outline/contents

ePix (0.1 FTE)

Charge numbers:

Medium/long term projects/deliverables

DeliverableComplete DateResponsibleBlockers/issues
ePix100A detector data sheet5/11Mark 
ePix100A installation guide5/11Mark 
ePix100A detector ops/api guide5/11Mark
  • Need to know if assembled detector can/will be
    pre-calibrated (ASIC calibration) and a config database
    delivered

TID-AIR General Work (??? FTE)

Most of these are wish listy items with no time or budget.

Medium/long term projects/deliverables

DeliverableComplete DateResponsibleBlockers/issues
Review permissions scheme for ppareg
Confluence space
 Mark 
Reorg and new navigation scheme for
ppareg Confluence spaec
 Mark 
Run interference with LCLS, LCLS-II doc
control and CDR/PDR/FDR and CD* review
prep.
 Mark 

JIRA Items

Jira
serverSLAC National Accelerator Laboratory
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject="ESLCOMMON" and status!="done" order by assignee
serverId1b8dc293-975d-3f2d-b988-18fd9aec1546