DeliverableComplete DateResponsibleBlockers/Issues
eTraveler standards, conventions,
best practices documentation. All Camera
subsystems must use.
4/2027/15Mark/Robert
  • (minus) Consensus from Camera project on core standards
eTraveler procedures for
raft electronics boards

???
(~5 days effort left,
waiting on BNL)

Robert
  • (minus) Final assembly process details from BNL
  • Coordination with Mark Bostic at SLAC for posting RGA
    results

...

DeliverableComplete DateResponsibleBlockers/Issues
Finish release of 0266 ICD4/2027Mark
  • Matt Boyes back 4/18. He will guide the doc out.
Finish release of Platform ICD4/20Mark
  • Out for approval according to Matt
Finish release of Timing ICD5/4/20Mark
  • Talk to Matt Weaver and Boyes on some scope still
    floating around
Finish release of HPS FRSs45/2711Mark
  • Get blessing from Matt Boyes on outline/contents
Finish release of HPS ESDs5/11Mark
  • Get blessing from Matt Boyes on outline/contents

...