Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

SVT chiller connected, filled, run. Fill level is just above 3/4 (highest non-alarm level). There is a little bit of coolant left in the plastic jug, plus three unopened bottles.

2015-02-11

Before attempting to take data, all of the FEB's were checked for sync.  The results are as follows: 

Summary: All APV's sync.

TKN - a longer exposition on the above:

  • FEB plate in - is cable clip in back really advisable?
  • must remember order: L46 hybrids, L46 data, L13 hybrids, L13 data
  • connected patch panel
  • connect flange to data last
  • lessons:
    • connection order: P4, P2, P3, HV2, HV2, P5, P1 ?
    • gentle with Dsubs!!
Found several ground faults:
  • Data cables were contacting flange and therefore shorting the following path:  Vacuum box -> mini-SAS shield -> mini-SAS ground -> FEB ground -> hybrid ground -> SVT detector ground (module, u-channel, box).  This is bad. 
  • Placed temporary mylar cone in flange.
  • Realized that bundling data cables will create flaky shorts among all FEB grounds.  Will need to passivate data cables over nearly their entire length in some way.
  • Found new short between SVT Box and Flange: ground lug on inside of flange meant for grounding the SVT was touching the flange.  Ground lugs have been covered in Kapton tape. Question: do we intend to use these?
  • Found short between FEB plate and SVT Box. Pins inside P4 were bent during connection and ground pin was bent into shell. This shorts the following path: FEB plate -> Patch panel -> connector shell -> FEB ground -> hybrid ground -> SVT detector ground (module, u-channel, Box).
  • Pins are redundant.  Pins were bent back into position as well as possible. Lower left pin has slight s-curve but pushed partway into pin block. Upper left pin has larger s-curve.  Both appeared to engage after repair but should be replaced.

2015-02-11

Before attempting to take data, all of the FEB's were checked for sync.  The results are as follows: 

Summary: All APV's sync.==============================================================
Physical FEB: 1t Serial: FebFpga: 2
Device DNA: 0x14084072beb01c00
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 11, DP 0, Hybrid N/A, N/A
DPM 11, DP 1, Hybrid N/A, N/A
DPM 11, DP 2, Hybrid 1, all sync
DPM 12, DP 0, Hybrid 0, all sync
==============================================================

==============================================================
Physical FEB: 2-3t 1t Serial: FebFpga: 02
Device DNA: 0x42084072beb01400 0x14084072beb01c00
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 1011, DP 30, Hybrid 3, all sync, APV 3 base value is lower than usual ~0x5f7
DPM 12, DP 3, Hybrid 2, all sync, APV 2 base value is lower than usual ~0x5de
DPM 13N/A, N/A
DPM 11, DP 1, Hybrid N/A, N/A
DPM 11, DP 2, Hybrid 1, all sync , APV 2 base value is lower than usual ~0x525
DPM 0812, DP 30, Hybrid 0, all sync
==============================================================

==============================================================
Physical FEB: 4t 2-3t Serial: FebFpga: 50
Device DNA: 0x58d04072beb01400 0x42084072beb01400
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 010, DP 03, Hybrid 3, all sync, APV 3 base value is lower than usual ~0x5f7
DPM 012, DP 13, Hybrid 2, all sync
DPM 0, DP 2, APV 2 base value is lower than usual ~0x5de
DPM 13, DP 2, Hybrid 1, all sync, APV 2 base value is lower than usual ~0x525
DPM 108, DP 03, Hybrid 0, all sync
==============================================================

==============================================================
Physical FEB: 5t 4t Serial: FebFpga: 85
Device DNA: 0x52814100a1b01c00 0x58d04072beb01400
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 40, DP 0, Hybrid 3, all sync , APV 1 and 4 base value is lower than usual
DPM 40, DP 1, Hybrid 2, all sync
DPM 40, DP 2, Hybrid 1, all sync , APV 3 base value is lower than usual
DPM 51, DP 0, Hybrid 0, all sync , APV 0 and 4 base value is lower than usual
==============================================================

==============================================================
Physical FEB: 6t 5t Serial: FebFpga: 78
Device DNA: 0x50814100a1b01c00 0x52814100a1b01c00
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 54, DP 10, Hybrid 3, all sync, APV 1 and 4 base value is lower than usual
DPM 54, DP 21, Hybrid 2, all sync
DPM 64, DP 02, Hybrid 1, all sync, APV 3 base value is lower than usual
DPM 65, DP 10, Hybrid 0, all sync, APV 0 and 4 base value is lower than usual
==============================================================

==============================================================
Physical FEB: 1b 6t Serial: FebFpga: 97
Device DNA: 0x24d04072beb01c00 0x50814100a1b01c00
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 105, DP 01, Hybrid N/A, N/A3, all sync
DPM 105, DP 12, Hybrid 12, all sync
DPM 106, DP 20, Hybrid 01, all sync
DPM 096, DP 21, Hybrid N/A, N/A 0, all sync
==============================================================

==============================================================
Physical FEB: 2-3b 1b Serial: FebFpga: 119
Device DNA: 0x02d04072beb01c00 0x24d04072beb01c00
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 710, DP 0, Hybrid 3, all syncN/A, N/A
DPM 710, DP 1, Hybrid 21, all sync
DPM 710, DP 2, Hybrid 10, all sync
DPM 809, DP 02, Hybrid 0, all sync N/A, N/A
==============================================================

==============================================================
Physical FEB: 4b 2-3b Serial: FebFpga: 111
Device DNA: 0x72814100a1b01c00 0x02d04072beb01c00
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 127, DP 10, Hybrid 3, all sync
DPM 127, DP 21, Hybrid 2, all sync
DPM 137, DP 02, Hybrid 1, all sync , APV 0 base value is lower than usual
DPM 138, DP 10, Hybrid 0, all sync
==============================================================

==============================================================
Physical FEB: 5b 4b Serial: FebFpga: 41
Device DNA: 0x1c084072beb01400 0x72814100a1b01c00
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 112, DP 1, Hybrid 3, all sync
DPM 112, DP 2, Hybrid 2, all sync
DPM 213, DP 0, Hybrid 1, all sync, APV 0 base value is lower than usual
DPM 213, DP 1, Hybrid 0, all sync , APV 3 base value is lower than usual
==============================================================

==============================================================
Physical FEB: 6b 5b Serial: FebFpga: 34
Device DNA: 0x70d04072beb01c00 0x1c084072beb01400
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 21, DP 21, Hybrid 3, all sync
DPM 31, DP 02, Hybrid 2, all sync
DPM 32, DP 10, Hybrid 1, all sync , APV 2 base value is lower than usual
DPM 32, DP 21, Hybrid 0, all sync, APV 3 base value is lower than usual
==============================================================

Hacked coda to run from ppa-pc91245.

Run 837, L4t, bias to H2 and H3 (some issue with mpod crate), 
Run 838, L4t, bias to all four hybrids.

Run 840, full detector, ET ring adjusted for large events. Note that there was an error on dpm7 when I hit "Go" (something with FebCore). Things looked ok and DTM0 say Ack on all dpm's.

SVT chiller flow switch tested. Drained and refilled chiller in the process; level is just above 3/4, jug is empty. Chiller is running at stage 3 (we got a pressure trip at stage 4, which has not happened before - not sure why); this will be our normal setting. Estimated flow (based on pressure drop vs. flow switch trip) is 1.5 GPM. SVT chiller is connected to Wesley's EPICS stuff; work in progress.

2015-02-12

FEB chiller setup simplified so we just have the flow meter and flow switch (no manifold). This will make it easier to swap hoses or add components if we decide to do that before installation. Flow is unchanged at ~5 GPH (bottom of the flow meter range, below the flow switch range).

Noise performance results of first full test with all FEB's and hybrids powered on and biased.  Only a single COB was setup to run with CODA.  Overall, the noise on all FEB's that we took data with looked as expected.

==============================================================
Physical FEB: 6b Serial: FebFpga: 3
Device DNA: 0x70d04072beb01c00
FpgaVersion: 0xb0000024
Control/Data Fiber: Flange:
==============================================================
DPM 2, DP 2, Hybrid 3, all sync
DPM 3, DP 0, Hybrid 2, all sync
DPM 3, DP 1, Hybrid 1, all sync, APV 2 base value is lower than usual
DPM 3, DP 2, Hybrid 0, all sync
==============================================================

Hacked coda to run from ppa-pc91245.

Run 837, L4t, bias to H2 and H3 (some issue with mpod crate), 
Run 838, L4t, bias to all four hybrids.

Run 840, full detector, ET ring adjusted for large events. Note that there was an error on dpm7 when I hit "Go" (something with FebCore). Things looked ok and DTM0 say Ack on all dpm's.

SVT chiller flow switch tested. Drained and refilled chiller in the process; level is just above 3/4, jug is empty. Chiller is running at stage 3 (we got a pressure trip at stage 4, which has not happened before - not sure why); this will be our normal setting. Estimated flow (based on pressure drop vs. flow switch trip) is 1.5 GPM. SVT chiller is connected to Wesley's EPICS stuff; work in progress.

2015-02-12

FEB chiller setup simplified so we just have the flow meter and flow switch (no manifold). This will make it easier to swap hoses or add components if we decide to do that before installation. Flow is unchanged at ~5 GPH (bottom of the flow meter range, below the flow switch range).

Noise performance results of first full test with all FEB's and hybrids powered on and biased.  Only a single COB was setup to run with CODA.  Overall, the noise on all FEB's that we took data with looked as expected.==============================================================
Physical FEB: 4t Serial: FebFpga: 5
==============================================================
Hybrid 3: Looks fine. Noise ~51 ADC Counts, high noise on edge channels and noise rise on APV 0, hump in noise of APV 0
Hybrid 2: Looks fine. Noise ~52 ADC Counts, high noise on edge channels and noise rise on APV 0, hump in noise of APV 0
Hybrid 1: Looks fine. Noise ~52 ADC Counts, high noise on edge channels and noise rise on APV 0, hump in noise of APV 0
Hybrid 0: Looks fine. Noise ~51 ADC Counts, high noise on edge channels and noise rise on APV 0, hump in noise of APV 0

==============================================================
==============================================================
Physical FEB: 5t Physical FEB: 4t Serial: FebFpga: 85

==============================================================
Hybrid 3: Looks fine. Noise ~51 ADC Counts, high noise on edge channels and noise rise on APV 0, hump in noise of APV 0
Hybrid 2: Looks fine. Noise ~50 ~52 ADC Counts, high noise on edge channels and noise rise on APV 0, hump in noise of APV 0
Hybrid 1: Looks fine. Noise ~52 ADC Counts, high noise on edge channels and noise rise on APV 0, hump in noise of APV 0
Hybrid 0: Looks  Looks fine. Noise ~50 ~51 ADC Counts, high noise on edge channels channels and noise rise on APV 0, hump in noise of APV 0
==============================================================

==============================================================
Physical FEB: 6t 5t Serial: FebFpga: 78
==============================================================
Hybrid 3: Looks fine. Noise ~52 ~51 ADC Counts, high noise on edge channels
Hybrid 2: Looks fine. Noise ~52 ~50 ADC Counts, high noise on edge channels and noise rise on APV 0
Hybrid 1: Looks fine. Noise ~52 ADC Counts, high noise on edge channels and noise rise on APV 0
Hybrid 0: Looks fine. Noise ~52 ~50 ADC Counts, high noise on edge channels 
==============================================================

==============================================================
Physical FEB: 5b 6t Serial: FebFpga: 47
==============================================================
Hybrid 3: Looks fine. Noise ~51 ~52 ADC Counts, high noise on edge channels
Hybrid 2: Looks fine. Noise ~50 ~52 ADC Counts, high noise on edge channels
Hybrid 1: Looks fine. Noise ~50 ~52 ADC Counts, high noise on edge channels
Hybrid 0: Looks fine. Noise ~49 ~52 ADC Counts, high noise on edge channels 
==============================================================

==============================================================
Physical FEB: 6b 5b Serial: FebFpga: 34
==============================================================
Hybrid 3: Looks fine. Noise ~54 ~51 ADC Counts, high noise on edge channels and noise rise on APV 0
Hybrid 2: Looks fine. Noise ~50 ADC Counts, high noise on edge channels
Hybrid 1: Looks  Looks fine. Noise ~51 ~50 ADC Counts, high noise on edge channels
Hybrid 0: Looks  Looks fine. Noise ~50 ~49 ADC Counts, high noise on edge channels and noise rise on APV 0channels 
==============================================================

==============================================================
Physical FEB: 6b Serial: FebFpga: 3
==============================================================
Hybrid 3: Looks fine. Noise ~54 ADC Counts, high noise on edge channels and noise rise on APV 0
Hybrid 2: Looks fine. Noise ~50 ADC Counts, high noise on edge channels
Hybrid 1: Looks fine. Noise ~51 ADC Counts, high noise on edge channels
Hybrid 0: Looks fine. Noise ~50 ADC Counts, high noise on edge channels and noise rise on APV 0
==============================================================

2015-02-13

Plan for next weekend:
  • Remove data flange and disconnect all cables.  Mark out desired lengths and passivation locations for all data cables. Clear all cables to inside of vacuum box for power flange removal.
  • Disconnect patch panel. Remove power flange.  Implement final grounding scheme on power flange.
  • Remove all data cables for passivation and/or replacement.  Fold and passivate data cables.
  • Install temporary lever support.  Disconnect linear shifts and flex pivots.  Remove linear shifts. Disconnect cooling and remove cooling feedthroughs.
  • Release vacuum box from top clamp. Remove cooling manifold. Remove vacuum box for packing.
  • Pull FEB cooling plate out as far as L1-3 allows. Remove P4 male DB44 from patch panel and cut all zip ties on those wires. Remove L4b LV mezzanine, if necessary. Replace lower-left pin and re-insert.  If pin doesn’t push in, then replace upper-left pin.  Otherwise; extract and mark all pins, replace upper left pin, reinsert all pins in new shell.  Reinstall P4 on patch panel.  Push cooling plate back into SVT box.  Use clamp to lock patch panel into SVT box. Use zip ties to lock lever lock into place?
  • Re-install L4-6 data cables. Re-install L1-3 data cables, if possible. 
  • Install hall probe in L6 electron-side window with DP190 and tape wire into place.
  • Secure loose data cables in SVT box. Tape foil to box from crane straps.
  • Lock lever lock into box for safety with clamp.
  • Lock L46 upper hanger with jam nut!
  • Prepare G10 pieces for SVT isolation.
  • Pack all needed items to take to Hall B for installation.
  • Prepare straps and tie-downs for lifts on Monday.
Plan for Monday:
  • Wipe down shipping plate from larger box and take into cleanroom on dollies. Lay foil along shipping plate for bottom of box. (15")
  • Release SVT from table.
  • Crane SVT onto shipping plate. (15")
  • Wrap and tape SVT box with foil. (15")
  • Roll SVT out of cleanroom. Cinch SVT down to shipping plate with tie downs. (15”)  *1’*
  • Install lid on inner box. (15")
  • Roll SVT out to crane area. (15")
  • Crane SVT into outer box.  Install foam. (15")
  • Close outer box. (15")
  • Crane outer box onto truck, levers facing rear, along with vacuum box and large crate with other items. (30”) *2’15”*
  • Slow truck move into Hall B down ramp. (30")
  • Crane inner box out. (15”) *3’*
  • Open inner box. (15")
  • Release SVT and crane up to pie tower. (15")
    • Pull SVT in and lower onto padded lift cart.
  • Move SVT to PS magnet (15")
    • Slow roll on lift cart to alcove.
    • Transfer to lift cart in alcove.
    • Lift up on cart, then shoulder-height lift to table in front of vacuum chamber.
  • Get SVT into position to transfer to vacuum chamber (15”) *4’*
  • Transfer SVT to vacuum chamber. (15”) *4’15*
  • Isolate SVT box with G10
  • Align SVT and lock into place (120")
Questions:
  • How heavy is the SVT?  Can we avoid the first crane lift with a manual lift?
  • Can we do to alignment on Day 1?