Item/Task | Owner | sub-item/task | Dates | Comment |
---|---|---|---|---|
FEB | Ben | |||
layout | Done 8/4 | |||
fabrication | 8/6-8/12 | |||
loading | 8/13-8/20 | |||
testing | 8/21- | |||
L4-6 Half-module production | Tim | |||
apv25 loading | 8/7 | |||
hybrid & sensor QA | 8/12 | |||
half-module production incl. QA | 8/19-8/29 | When Tim is back. | ||
L1-3 Module assembly | Tim | |||
L4-6 Module assembly | Tim | |||
Mechanical dry run assembly | Shawn | |||
w/o cabling and real FEBs (but cold plate) | 8/8 | |||
Motion control system check | Takashi | 8/15 | ||
Survey | Tim/Takashi/John | overview and procedures needed | ||
Modules | ||||
U-channels | ||||
SVT full assembly survey | ||||
Internal cabling | Tim/Dave | |||
FEB mezzanine card layout | 8/8 | |||
FEB mezzanine card fabrication | 8/15 | |||
Hybrid mezzanine card layout | 8/13 | |||
Hybrid mezzanine card fabrication | 8/20 | |||
pre-production bundle fabrication | 8/21-8/26 | |||
pre-production bundle test with FEB | 8/27-9/3 | |||
5. Module assembly L1-3 6. Module assembly L4-6 7. Survey--modules, u-channels, overall overview and procedures needed 8. Mech assembly dry run 9. Motion control system check 10. inner cables-- layout, assembly, and test 11. meazzanine boards--layout, fab, load, test 12. target--design, fab, check 13. wires--design, fab, check 14. flange cards 15. outer power cables 16. Chiller and cooling system checkout 17. PS checkout 18. Shipping boxes