  • Current performance results for the Pass8 code are on this page .
  • For 20,000 event clumps:

    job step

    average CPU time

    processClump

    183 min

    mergeClumps

    10 min

  • Plot of job throughput as of 20130813

    From the plot, one can see a processing rate of ~208 runs/day. Assuming 28500 total runs, this would mean a repro time of 137 days or 4.5 months.
  • Another plot showing the number of run scratch directories cleaned up per day: