Minutes

Present at JLab: Krister, Ani, Nerses, Stepan, Hovanes

Present at SLAC: Sho, Pelle

Magnets
  • Krister have not had much time to work on magnet cotrolscontrols
  • Krister will needs to install the beam stopper motor cables now.
  • Beam viewer motor cables will be next.

...

  • Pelle is working on specifications for the hybrid LV and BIAS channels for SVT.
  • He will have a discussion with people at SLAC and send Hovanes an e-mail how to proceed with DAQ CA server.
Interlocks
  • Krister and Hovanes installed the SVT interlocks chassis in the Hall B counting house
  • We need to decide what PLC programming licenses to use"
    • Use CLAS12 license if CLAS12 is buying one
    • Try to use Hall D license while they are not using it
    • Likely date of SVT arrival to JLab is the middle of August.

Action items

  • Krister will install the cables for the beam stopper and beam viewer.
  • Hovanes will send an e-mail to takashi Takashi about using homing without "Index" signal from the encoder.
  • Hovanes will discuss with Sergey and Ken the possibility of using CLAS12 PLC licenses.
  • Hovanes will implement fake records for the hybrid low voltages on the SVT voltage IOC.
  • Pelle will send Hovanes en email about the plans to develop the DAQ CA server.