Run Checklist

The following info must MUST be checked/reported for every shift

for each run enter in the elogbook 

...

- MNP17 current settings (if applicable) 

- note notes (e.g. beam intensity, no-beam time, loss of synchronization, change of configuration such as magnet settings, table position)

for each run monitor in the on-line monitor 

- DAQ synchronization (check the diagnostics panel, in particular the top left plot should have hits only in the band +-50ns)

for each run monitor in the AD on-line monitor 

- for each chamber check the histogram showing the number of hits, if it shows events with more that 128 hits, it means that the pedestal of the Si chambers of the tagger has shifted and must be refreshed. Do the following:

- take a pedestal run in the ancillary

- refresh the pedestal file for the CU online-monitor and for the AD DAQ 

for each shift check the following 

- CU temperature, every 2 hours, either monitoring the housekeeping data from RunControl or the CU data-logger, which you can see by looking at VNC monitor on pcglast22

- Cerenkov pressure, once a shift 

 

The following is a more detailed list of duties for shifters. 

 This is a list of steps to be followed while on shift. Please note that when we change configurations some of the reference plots may also change

...

Set Table in the Correct Position using this document. Details about the table can be found here

Tune Beam - ONLY IF REQUIRED BY THE PROGRAM - consult an expert if needed

Start and Stop a Run

Check Beam Status 

Required info to enter in the elogbook for each run

- run number

- scaler counts (S0, HW trigger, S0&C1&C2,NotSh&S2,DAQ TRIG)

- trigger setup

- synch with AD ON or OFF

- notes 

Start a run

Start a run

Select a data taking configuration for the CU (see here for details)

End a run

Online Monitoring

...

  • ACD Page
  • Ancillary 1  page
  • Ancillary 2  Page
  • Ancillary Detail  Page
  • Statistics Page
  • Check TKR, CAl and Statisctics Pages  for TEM 1, 2, and 3 
  • Check the trigger counting rate

Offline Monitoring

 

Data Taking Configurations

In the

Predictions from MC Simulations

In the

Tune the Beam - Expert

 Nice During daytime, the 4th shifter must run the Offline monitor to monitor relevant plots and compare with MC data sets