Run Checklist

The following info must be checked for every shift

for each run enter in the elogbook 

- run number (from RunControl)

- run type (photon data, electrons, positrons, proton and in particular if a test or calibration or pedestal run) 

- scaler counts (S0, HW trigger, S0&C1&C2,NotSh&S2,DAQ TRIG) - from Online monitor or directly from scalers in the top NIM crate

- trigger choice (if external verify its setup in the trigger logic and in the BT configuration, if internal make sure you  select the right BT configuration)

- synchronization with AD ON or OFF; if OFF take a look at AD plots and comment on anomalies

- table position (check it is automatically entered from the pop-up GUI at start of run)

- particle type (e.g. tagged-photons, full-brem, e, pion, proton, positron)

- MNP17 current settings (if applicable) 

- note (e.g. beam intensity, no-beam time, loss of synchronization, change of configuration such as magnet settings, table position)

 

 

 This is a list of steps to be followed while on shift. Please note that when we change configurations some of the reference plots may also change

...