Program Priority (to be agreed) 

Considerations

  • We lost about 7 to 10 days of beam because of problems at CERN
  • Some of the experts that arrived for the initial weeks of the beam test will leave around Aug 8, which is the first day we will have the beam
  • Should consider taking data as soon as beam turns on since the likelihood of problems is high. Focus on simple tests first. 

Here is a list of items we want to prioritize

  1. Measure PSF from 20 to 3 GeV
  2. d
  3. d
  4. d
  5. d
    fd 

Program prior to

...

start of beam test

This is a result of the discussions we had in Pisa is captured in this spreadsheet 

Proposal 1 for trade-

...

off after 1 week of no beam

Gary's preliminary estimates do not yet include