The software comprising the pipeline and what it runs is under configuration control for the remainder of the GLAST Beam test period. After baselining the code, all modifications to the running code will need to be approved by the Change Control Board. The purpose of configuration control is to understand the code content that affects processing results, and to maximize system uptime by vetting changes that affect reliability.
CCB Actions List
Blog Posts | ||||||||
---|---|---|---|---|---|---|---|---|
|
Process
Proposed changes will be submitted to the CCB with an explanation of the need, changes and consequences. These will be recorded in blogs in this confluence space. Approval will be recorded here also. Consideration and approval may be done via email, vrvs meeting or phone depending on the urgency of the request. We will start off by requiring unanimous approval from the board members for the action to be approved.
...