Migration from the old server to new server, 10g to 11g
Distilled Steps (Estimated 30 work days to completion, 6 calendar weeks)
- Take outage, Migrate pipeline and datacat dev database to new server
- Test out new server on Pipeline-II 1.4
- Test changes on new Pipeline-II 1.5 branch
- Take outage, perform pipeline and datacat prod TEST migration
- Test out temporary trending database, L1Proc at scale
- After Pipeline/datacat prod migration TEST, schedule actual migration
- Run migrated production pipeline on temporary trending table space for a few days
- After the trending database is migrated to the new server, update it with temporary trending values
- Swap to permanent trending database
Test migration of GLAST_DP_TEST tablespace (pipeline and datacatalog tables)
...