Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

We would like to do this in 3 installments:

A. Switch over one over three sector whose klystrons are active on the beam, preferrably
near the end of the Linac . 2 (say LI26-LI28). 3 hours

B. If A goes well, 1at least 2-2 3 days later, switch over LI20, LI29, LI26- LI30. 4  3 hours

C. If B goes well, 2 at least 2 or more days later, switch over remaining sectors LI21-LI25. 3 hours

2. Systems Affected:

...