numbering scheme corresponds to ECal software task list
1 Simulation
a) Geometry updates – February ~1 month
b) Digitization and Electronic Noise – Commence in November and complete by end of 2013
c) Data production for ECal group – ready
2 Reconstruction
b) Testing cluster algorithms – November into December
c) Evaluate sampling fraction – December/January
d) Cluster position corrections (e+/e-/gamma), depends on 2 b), needed before e), f), g) – January/February
e) Cluster timing, depends on 1 b) – February
f) Cluster pattern, needs 2 b) – January/February
g) Matching with tracking, needs 2 d) – March
3 Monitoring
a) Cosmic trigger and reconstruction – January/February
b) Light monitoring system software – December (ready to communicate requirements to slow controls group)
4 Calibration
a) Track based calibration, requires completion of reconstruction tasks – April/May (projecting 2 months)
b) Pi0 reconstruction – April/May (early start with cross sections possible)
c) Cosmics, linked to 3 a) – March/April
d) Single electron scattering – December/January
e) Position correction, based on 2 c) – February/March
5 Trigger Studies
b) Trigger algorithm studies at board and crate level – January to March
c) Rates of physical noise – March
d) Algorithm optimization – April to June
6 Online software – May to July