Agenda:
- Update on beam line installation - hall status (pdf) François
Francois showed a few photos of recent installation activities
- Report on test of linear stage in B-field - 2014-05-12Bfield.pptx 2014-05-12Stage.pptx(Takashi) 
Takashi presented results on the tests of the linear stage in a B-field
 
- Are there other beam line procedure documents required (besides the "Beam on Initially" procedures)? 
e.g.
"How to operate the HPS PC" 
"How to operate the HPS primary target".
"Beam operation manual for shift person"
- Are the survey requirements for the beam line understood? Do the Hall B people need anything more from us? 
- Other?
  • No labels