Present:   John, Rafo, Maurik, Tim, Marzio, Matt, Norman, Cameron 

  • News: Limited work at SLAC, work is progressing. The summer run at JLAB is as difficult as the last summer. Safety meeting tomorrow for SAD work on JLAB site, rules will affect HPS work. 
  • Preparations for PAC jeopardy presentation - Tim
    An email was sent to the presenter with three bullets, with questions that presentations should address. The jeopardy document and plans for the presentation included these questions. There is 20 min for HPS, 15 min for presentation, and 5 min for questions.  
    • Reach plots - Cameron
      2019 and 2019+2021 vertexing reach was presented, will be as a backup if questions arise
    • 2016 analysis results - Matt
      L1L1 results from Matt and what Rafo and Cameron have, should we show updated 2015 - probably no, it was not in the jeopardy document.
    • 2019 detector performance - Norman
      New plots will be prepared by the end of the week 
  • Discussion of working groups and EC coordinators (if time permits)
  • aob
  • No labels