Present: John, Maurik, Marzio, Cameron, Matt G., Rafo, Stepan, Omar, Nathan, Norman
Some tests of remote shifts (Alessandra). Should send another email to get remote shifters to test the system. Some improvement to the documentation will be needed. Also need a backup for remote shifts. Will need to send email for missing shift assignments.
More volunteers for RC are needed, the expert on-call list is almost complete.
Documentation has been submitted to DSO to get the run certification (any day now). Some manuals and commissioning documents need update.
FEBs are installed on the cooling plates, 8 out of 10 are good, two will be replaced. Modules on L1 and 2 have been replaced and tested. There are some damaged APVs on old modules close to the beam plane.
ECal chiller is getting installed today. Cosmic counters are installed, cosmic data taking will start soon. Hodo is in the hall ready for installation. Cable work is complete.
Putting upstream beamline together started, the beam pipe though torus will be in place by end of this week.
DAQ work is in progress, should be ready by the end of week
Old stuff is ready. Working on the new DQM, should be ready by the start of the run with the documentation.