Present: John, Maurik, Marzio, Cameron, Matt G., Rafo, Stepan, Omar, Nathan, Norman

  • News: JLAB, makes required. MCC presentation on HPS at the last Wednesday meeting. Run start is still on 23rd.
  • Shift sign-up - Marzio/Maurik

Some tests of remote shifts (Alessandra). Should send another email to get remote shifters to test the system. Some improvement to the documentation will be needed. Also need a backup for remote shifts. Will need to send email for missing shift assignments.

  • List of RC and experts on-call - Stepan

More volunteers for RC are needed, the expert on-call list is almost complete.

  • Documentation - Stepan

Documentation has been submitted to DSO to get the run certification (any day now). Some manuals and commissioning documents need update.

  • Preparations for the upcoming run:
    • SVT - Tim/Cameron

FEBs are installed on the cooling plates, 8 out of 10 are good, two will be replaced. Modules on L1 and 2 have been replaced and tested. There are some damaged APVs on old modules close to the beam plane. 

  • ECal/Hodo - Rafo

ECal chiller is getting installed today. Cosmic counters are installed, cosmic data taking will start soon. Hodo is in the hall ready for installation. Cable work is complete.

  • Hall/beamline - Stepan

Putting upstream beamline together started, the beam pipe though torus will be in place by end of this week.

  • DAQ/trigger - Omar

DAQ work is in progress, should be ready by the end of week

  • DQM - Matt G.

Old stuff is ready. Working on the new DQM, should be ready by the start of the run with the documentation.

  • Slow controls and remote shifts - Nathan