  • Does everyone have a Yubikey?
    • YES
    • Sebastian also recommends Cardinal Key
  • Beam turn-on
    • Lauren's current best estimate (optimistic) is 2-Oct
      • Could be pushed up with coordination
    • Lauren: check status for emergency detuning chassis checkout
    • Need to get to resonance on all available cavities
  • Green LCLSHome
    • Power back on 10-Sep
    • Water needs to come back on (no clear ETA)
  • Cryo back to 2K the week of the 16th
    • Week of the 23rd back to 4K
  • Lisa would like to do Q_0 calibrations when cryoplant is at 2K and not doing other activities
    • Sebastian thinks that most of the cryo plans are downstream: CM02, CM03 are likely available
  • Plan is to multipact-process some cryomodules in L3 as proof-of-concept during startup
    • Lisa has been working on GUI-fying this
    • Between 4 and 6 cryomodules have a potential for large gradient gains
    • When we make a plan for processing, should move Decarads
  • Update Smartsheet for on-call availability
  • Ryan reports that new cards for SSA fan fault avoidance are ready for testing
    • Need to find worst offender SSAs for testing
  • Any JLab testing updates?
    • Run from September 16 - October 14: nobody is available for that
    • Run from November 11 - December 9: no updates on this run