Confluence and Jira now require federated login. Read more.
Date
Attendees
Discussion Items
- Does everyone have a Yubikey?
- YES
- Sebastian also recommends Cardinal Key
- Beam turn-on
- Lauren's current best estimate (optimistic) is 2-Oct
- Could be pushed up with coordination
- Lauren: check status for emergency detuning chassis checkout
- Need to get to resonance on all available cavities
- Green LCLSHome
- Power back on 10-Sep
- Water needs to come back on (no clear ETA)
- Cryo back to 2K the week of the 16th
- Week of the 23rd back to 4K
- Lisa would like to do Q_0 calibrations when cryoplant is at 2K and not doing other activities
- Sebastian thinks that most of the cryo plans are downstream: CM02, CM03 are likely available
- Plan is to multipact-process some cryomodules in L3 as proof-of-concept during startup
- Lisa has been working on GUI-fying this
- Between 4 and 6 cryomodules have a potential for large gradient gains
- When we make a plan for processing, should move Decarads
- Update Smartsheet for on-call availability
- Ryan reports that new cards for SSA fan fault avoidance are ready for testing
- Need to find worst offender SSAs for testing
- Any JLab testing updates?
- Run from September 16 - October 14: nobody is available for that
- Run from November 11 - December 9: no updates on this run
Action items
{"serverDuration": 72, "requestCorrelationId": "a83ca0bf2f5b0cab"}