Date

Attendees

Goals

Discussion items

TimeItemWhoNotes
10 minShut down prepSebastian + Janice
  • We need to finish making list of things for Ops to shut off/do/don't do
  • Don't close valves near CMs if not necessary
  • Linac turn off will be July 4th at 8am. 
    • Tentatively Sebastian and Lauren  
10 minFuture PAMMsSebastian
  • Spacing of PAMMs will stay the same
  • There will be one POMM a month for SRF
    • This includes RF work, magnet work, software updates/tests
    • Tentatively on Weds
    • Will coordinate with LLRF group for RF work
    • Could include some real time cavity testing after adjustments
5 minSafety pauseSebastian
  • Do training, finish documentation, look for CATERs that can be closed.
  • Go to SAGE poster session

Action items