Discussion items
- Sebastian is on vacation 6/3-6/12
- Ryan will be acting area physicist
- New shifts are on the calendar
- Hailey has accepted the Al Ashley fellowship!
- AFS migration happening soon
- Control system is already on NFS
- No news on a new deadline
- Nicole will research and send something in the group chat
- SLAC Summer Lunch on 6/20 - make sure to RSVP
- SLAC Run and Walk is Weds, 6/5
- During the PAMM
- Roads to/from the klystron gallery will be blocked from 11:30-1 pm
- Lauren to move decarads next week
- Lauren should make a job to move Decarad 2 from CM33 → CM32 during the following PAMM
- PAMM frequency changes being mulled over
- Andy points out to CAMs that charges might be less with less PAMM planning time
- Many stakeholders, so TBD
- CMH1-4 & CMH2-4: follow up on these cavities
- SSA drain voltages
- Come up with a plan to adjust globally
- Any global false quench issues over the past week?
- One of the power amps had dipped low the last time that occurred
- Phases(?)
- Larger diurnal temp swings → larger PRL phase swings → starting to get to the red/yellow EPICS alarm thresholds
- Automate PRL offset zeroing during phase scans
- Sonya can work with the GUI owner
- Study historical offsets during phase scans
- Interface with the Justin/FJD effort to implement a feed forward
- Look into the phase drift vs. linac Z
- What is the diurnal variation in tunnel temps?
- BSA rolled out in a couple of CMs two PAMMs ago!
- Planning on deploying globally after the next PAMM
- Deployed in CM31 & 32, but one of the racks is not working
- What are the issues with high rep rate
- Need to ramp up to 10 kHz, not just slam it on
- At least until the LBNL collab work is done