10/05/2023: L-10136 Checkout spreadsheet

MFX Pre-beam Checkout
AreaTaskDate CompletedComment
Vacuum



  • Gate Valve Permissions



  • Passed RGA Qualification



  • Beamline fully under vacuum


Radiation Physics



  • HPS certification valid



  • BLA signed



  • Test hutch search performed



  • RSWCF forms all closed

 






  • Administrative procedures for CRLs ready



  • Modifications to focusing optics approved



  • Hutch online


Controls



  • Checkout complete



  • Stability level tested



7/9/23 - LBG

  • Vacuum all tested



  • Gate valves tested



  • Interlocks functional and tested



  • Scripts ready and test



  • Hutch-python tested
7/9/23 - LBG

  • Cameras tested
    • fee_spec
    • mec_yag0
    • xcs_yag2
    • mfx_dia_yag
    • mfx_dg1_yag
    • mfx_dg2_yag
    • mfx_dg3_yag
  • Web Cameras
    • webcam-mfx-north
    • webcam-mfx-northeast
    • webcam-mfx-southeast
    • webcam-mfx-southwest
    • webcam-mfx-east

7/9/23 - LBG






7/10/23 - SM



  • Beam transport path clear and tested



  • X-ray Optics ready and motion tested



  • Switching between timing systems ready



  • Time tracking eloggrabber works


DAQ



  • Checkout complete



  • Scripts tested



  • Hutch-python tested



  • Stability level tested



  • Switching between timing systems ready



  • Test data recorded


PMPS





  • Verify that there are no PMPS faults 


Beamline Components


XRT
  • MR1L4
    • Set mirror IN works
    • Set mirror OUT works
    • Set coating W works
    • Set coating SiC works
    • Move mirror pitch -500 to 500 µrad


DIA
  • Pulse Picker
    • Move to open position
    • Move to closed position
    • Flip-flop mode

 



  • Attenuators
    • All attenuators close/open
    • MFX3 att(0) works correctly.
    • MFX3 att(1E-99) works correctly.
    • MFX3 att(1) works correctly.
    • Verify 0 and 100% are determined correctly in MFX home

 



  • Prefocusing Lens
    • Lens 1 inserts and removes.
    • Lens 2 inserts and removes.
    • Lens 3 inserts and removes.

 



 


DG1

 



 



 


TFS

DG2








 



  • ATM (timetool)
    • CamViewer Visualization
    • Move to any "IN" target
    • Producing an Image on CamViewer 
    • Check X motion
    • Move to "OUT" target


TAB

 


DG3


DET
  • Detector Table
    • Verify detector floor interlock works.
    • Verify table moves.











  • No labels