Attendees: Abigail, Elena,Josh, Rebecca, Armin, Will, Patrick, Dennis, Connor
Announcements:
Discussion:
- Mirror Substrates TPRR - received report
- ESDs updated and released
- TPR - being signed off
- procurements -
- procurement req is making way through approvals - where is it hung up? (reassigning account numbers) Armin to help Will
- ASP complete
- SSP
- RFP out soon
- procurement req is making way through approvals - where is it hung up? (reassigning account numbers) Armin to help Will
- Mirror chambers - ESD and SOW out for approval/
- Controls -
- chamber vendor provides chamber motion controls per controls level 3?
- SLAC provides bender controls independently
- what are the interfaces to controls? (in ac
- break-out meeting for controls (Armin, Elena, Will, Mitchell, Maggie, Rebecca)
- start the req?
- MFX Optics System review (peer review)
- system integration details
- chamber details (what we're asking for)
- how system will fulfill requirements
- Controls -
- Laser Transport EPR -
- FEH configuration updates
- enough info to start working out transport options
- CXI/MFX stakeholder updates
- decisions and path forward on September timeframe
- FEH configuration updates
- Lasers PDR - Mid August?
- ESD progress taking some resource efforts away from pdr prep
- Doc preparation
- Slides being prepared by Dennis
- mechanical detail follow-ups
- Controls
- looking at documentation
- review on wednesday?
- see if components fit on stands?
- Infrastructure -
- Met with Hannah - Control Room RDS
- Hannah is also developing mezzanine RDS - looking at loading in the FEH
- MFX RDS will be ready for interim release once we update rack items
- House Nitrogen - should we consider in present RDS? even though implementation is far in the future?
- control room RDS - not in project scope but we should provide feedback: https://slac.sharepoint.com/:w:/r/sites/lcls/lcls-2-he/exp/shared_docs/Experimental%20Systems/MFX/FEH%20Reconfiguration/FEH%20Hutch%204.5%20MFX%20Control%20Room_RDS%20%5B69%5D.docx?d=w82778d072cc34bf8a25fe887fbfbdc59&csf=1&web=1&e=JWrwbF
- rackspace - Mitchell met with Omar(IT/Data), Matt(BCS), (PPS) - follow ups next week? stakeholders needing space first
- BCS needs to confirm space requirements
- Handed off information/presentation to Diling
- will need to look out for the mezzanine RDS - will need to add penetrations? power requirements? we'll need to touch base with Hannah
- CC's
- YAG manufacturers 105mm MAX?
- vacuum based btm concept back in play? meeting soon?
- kitting meetings 2 hours tuesdays/thursdays
- what actually needs kitting?
- Armin to attend tomorrow
- strategy is work in progress
- Mechanical -
- CXI/MEC beamline stands/ valves
- met with CXi and MEC teams a few weeks ago to discuss interfaces
- Jim finalizing stand relocations
- Infrastructure
- RDS updates
- rack layout
- Elena working through collimator supports
- positions in section A are dialed in
- CXi is adding a collimator next to PC2L5, PC2L4
- BTm connectors interfering?
- Design of shielding in hutch 4 - waiting for final requirements but basic design near completion
- IM2L5 - location
- needs a stand name
- developing 2D drawings- working with Igor
- BIO seismic - mostly complete - hilti question
- IM2L5 - location
- BCS sensor counts - looking at gate valve ties, etc
- need to look at diffraction issues in the hutch
- Mirror- is there a published note? MFX specific? Will will generate? Or edit DXS note?
- redundant sensors?
- need to update note
- need to look at diffraction issues in the hutch
- Diffraction - start building a note like in XPP?
- XPP style Side boards would work for lasers?
- re-do BIO
- ejection and ATM
- Mechanical team will engineer these systems (jim charge laser number?)/ Laser team will assist with analysis
- MODS table location updated
- final design for structure still in the works
- Components to be added to tables
- CXI/MEC beamline stands/ valves