Attendees: Leinani, Elena,Josh, Rebecca, Armin, Dennis, Will
Announcements:
- Rebecca out June 27-July8
Discussion:
- Mirror Substrates TPRR - received report - updating drawings and ESDs- aiming to complete by end of week
- procurements -
- Req started for substrates (number?)
- ASP started
- Eliazar will approve on Armin's behalf
- procurements -
- Laser Transport EPR - report received from Brice
- FEH configuration updates
- 400W baseline
- Lasers PDR - Week of July 15?
- Doc preparation
- Slides being prepared
- LCLS FEH workshop -
- FEH laser room layout preferences (2 proposals for A/E to review)
- not clear on long term needs?
- Joe to reach out to leads
- rackspace - Mitchell met with Omar(IT/Data), Matt(BCS), (PPS) - follow ups next week? stakeholders needing space first
- BCS needs to confirm spac requirements
- FEH laser room layout preferences (2 proposals for A/E to review)
- Infrastructure -
- Met with Hannah - Control Room RDS
- Hannah is also developing mezzanine RDS - looking at loading in the FEH
- MFX RDS will be ready for interim release once we update rack items
- House Nitrogen - should we consider in present RDS? even though implementation is far in the future?
- control room RDS - not in project scope but we should provide feedback: https://slac.sharepoint.com/:w:/r/sites/lcls/lcls-2-he/exp/shared_docs/Experimental%20Systems/MFX/FEH%20Reconfiguration/FEH%20Hutch%204.5%20MFX%20Control%20Room_RDS%20%5B69%5D.docx?d=w82778d072cc34bf8a25fe887fbfbdc59&csf=1&web=1&e=JWrwbF
- Mechanical -
- Elena working through collimator supports
- CXi is adding a collimator next to PC2L5, PC2L4
- BTm connectors interfering?
- Design of shielding in hutch 4 - waiting for final requirements but basic design near completion
- developing 2D drawings
- BIO seismic
- BCS sensor counts - looking at gate valve ties, etc
- need to look at diffraction issues in the hutch
- Mirror- is there a published note? MFX specific? Will will generate? Or edit DXS note?
- redundant sensors?
- need to look at diffraction issues in the hutch
- XPP style Side boards would work for lasers?
- ejection and ATM
- Mechanical team will engineer these systems (jim charge laser number?)/ Laser team will assist with analysis
- ATM reversal - which model number would we end up with? Leinani send part numbers to Jim/Elena -34755?
- Reference laser reversal - backpack and laser on same side??? - Leinani
- MODS table updated.
- Components to be added to tables
- Elena working through collimator supports