Attendees: Will,Alex, Rebecca, Busse, Serge

Discussion:

  • Design Progress
    • Chamber Interface and Envelope - horiz. complete; vert almost done.
      • Randy is working on mechanical interface; working on cooling
  • ESD Progress
    • Bender - In house procurement so drawings will serve as the document
      • Engineering note explaining analysis and design choices + drawings? (will also need assembly traveller later) ; to supplement existing L2SI documentation?? ask May Ling
        • complete by end oct - driving review date
    • Chamber - ESD in work 80% (-0900 MFX - not combined with CXI - Title?)
      • motion table in work - supporting doc
      • Will will upload - on working doc site
    • Mirror/Coating - ESD in work 90% (-0895 MFX - Title?)
  • large displacement mirrors (in plan for DXS, CXI) - but not in plan for original MFX - need to specify this feature if we need it (also impacts radiation safety, exit flanges?, etc - other impacts to be consider)
  • Schedule - next milestones
    • CXI KB FDR - 10/18 - more of a PDR , or push FDR
    • SOW? - see
    • MFX KB FDR?- plan is 10/27/2023
    • DXS Offset Mirrors FDR- 12/05/2023
    • TPRR? (CXI vs MFX) - CXI might need an FDR review due to the focus scheme
    • For MFX:
      • FDR - Octoberish
      • SOW
      • TPRR