Attendees: Will,Alex, Rebecca, Busse, Serge
Discussion:
- Design Progress
- Chamber Interface and Envelope - horiz. complete; vert almost done.
- Randy is working on mechanical interface; working on cooling
- Chamber Interface and Envelope - horiz. complete; vert almost done.
- ESD Progress
- Bender - In house procurement so drawings will serve as the document
- Engineering note explaining analysis and design choices + drawings? (will also need assembly traveller later) ; to supplement existing L2SI documentation?? ask May Ling
- complete by end oct - driving review date
- Engineering note explaining analysis and design choices + drawings? (will also need assembly traveller later) ; to supplement existing L2SI documentation?? ask May Ling
- Chamber - ESD in work 80% (-0900 MFX - not combined with CXI - Title?)
- motion table in work - supporting doc
- Will will upload - on working doc site
- Mirror/Coating - ESD in work 90% (-0895 MFX - Title?)
- Bender - In house procurement so drawings will serve as the document
- large displacement mirrors (in plan for DXS, CXI) - but not in plan for original MFX - need to specify this feature if we need it (also impacts radiation safety, exit flanges?, etc - other impacts to be consider)
- Schedule - next milestones
- CXI KB FDR - 10/18 - more of a PDR , or push FDR
- SOW? - see
- MFX KB FDR?- plan is 10/27/2023
- DXS Offset Mirrors FDR- 12/05/2023
- TPRR? (CXI vs MFX) - CXI might need an FDR review due to the focus scheme
- For MFX:
- FDR - Octoberish
- SOW
- TPRR