Attendees: Marc, Alex, Armin, Eliazar, Joe (first half), Rebecca
- Matt thinks WFS spacing looks ok per 8/9 email
- Check XRT stopper clearance - alex thinks the space looks tight.
- Alex will check bases/versions of IPMs we have now - but we do have 3 chambers to reuse
- Facilities coordination - need to start discussing
- Detector Cooling
- Room Temperature control - can we control temperature locally at MODS table? easier?
- JJ visit - questions about sticky slits
- Armin added LOC to functional diagram
- Detector - current plan? 2M only? 2M +140k?
- 8M preferred
- Alex will create a summary of what we can achieve with each so we can do a cost/benefit analysis