Attendees: Armin, Rebecca, Eric, Eliazar, Alex, Marc

Discussion:

  • sample refrigerator dimensions (we like it to live between diamond window and sample table) 7cuft 31x27x32
  • Waiting for WFS calcs from Matt Seaberg- He's on leave . return 7/19/2021
    • His guess is that it's ok, but needs to do simulations
    • he also needs KB location - rebecca will send
  • Waiting for beam trajectory in KB mirror model - Received a new model # from Danny and we are aligning downstream diagnostics
    • DSG-000018006
  • Coordination with laser team is ongoing - underneath the raised floor is still leading concept (coord with Gerald Balanon at a later date )
    • "throw the cat among the pigeons" - slightly wider table (4 feet) is being considered. can it be placed over the cxi beampipe (overlapping)
      • stability?
      • we need to maintain access to the controls under the diagnostics
      • they need to maintain access to their laser related diagnostics - swapping ATM and the pumping cross
    • custom (taller) Mirror box with extension collar (extra height hidden under floor)
    • interference with "X"? Model validation...
    • MFX/Laser ICD - Dileep will send when readu
    • access to controls under diagnostics raft is going to be tricky - should we start coordinating with controls on new placement scheme?
    • Michael Greenberg requested some dimensions
    • temperature stability/humidity requirements
      • Alex : very warm when we're running, cools off by a few degrees when hutch is open
      • Data from Kingston?
      • Need to address?
  • Need to evaluate if we have enough pumping to reach Level 1 pressures (we likely need to add pumps to new layout)- Rebecca to analyze
    • Current gauges in MFX read:
      • MFX-DG1-01 4.2e-09
      • MFX-TFS-01 6.3e-09
      • MFX-DG2-01 1.2e-08
  • RP meeting needs to be set up. - Mondays 1-2pm
    • XRT Raytrace
    • Dump ?
    • CXI beam - hutch access still ok? mirror?
  • CAD model clean up
    • Laser model incorporated into top level
  • Transfocator – Alex to capture lessons learned - is there an email about this? (backlash)
    • lenses loaded now: (per Alex from -z to +z) 500, 300, 250, 200,125, 62.5, 50, 50, 50
    • Be is O-30-H
    • units in microns
  • Facilities coordination - need to start discussing
    • Detector Cooling
    • Room Temperature control
  •  IDCs
    • Laser ICD ready to review
    • other systems?
    • 2nd pass through device list. (due in 3 weeks)
  • ESDs
    • For whole endstation or for particular subsystems?



  • No labels