Attendees: Gilliss Dyer  Walter Wittmer Ginger DeContreras Mikael David Martinez Pointing stability; getting on the same page with LLNL; working on ops model; alternate flagships for alternate laser

Discussion items

ItemNotes
2nd PetawattDraft a technical note.  A. Conder suggests that B. Arnold, R. Plummer and C. Rossignol create a draft.  KL suggests using framework: https://docs.google.com/spreadsheets/d/1exSima23Ks0vDDqH0QNiwMH0L3CFk1hkNk-wHy5Q30c/edit#gid=0, 5/9/24 update: no progress but welcome.
RR-SP pointing stability
Radiation Source Term
Spatial ChirpNeed more information.
Global Requirements Workshop

Other

  • Mikael provided update on where we are with FES budget exercise.
    • Impacts to Science: Single seed laser.  One Amica, amplified, split, then normal amplification.  Or stacked system.  Removed 20' from Laser Hall.  Gilliss:  DMPL?  RR-SP to seed?  NNSA possibility could add space.
    • No change to TAX
    • Impacts to ConOps: Removed both shield walls.  No laser shots with people in the Laser Hall.  Cavern 258 ft > 169 ft.  Removed vestibule.  Gilliss: Time to search entire area should be considered.  Include in contingency.

Topics for Next Time

  • Document Radiation Source Term assumptions

Action items