ATTENDEES:

Kukhee, Diane, Steph, Debbie, Partha, Patrick, Terri, Dan, Hamid, ..

ANNOUNCEMENTS:

Diane will be on vacation from July 8 through July 19; our next Friday meeting will be July 24. Please see Debbie Rogind for general Fast Feedback project questions while Diane is away.

TOPICS:

We discussed Kukhee's multicast testing and brainstormed ideas for setup changes and further testing. Kukhee will first try his test using two multicast groups instead of the one group. If this does not show improvement, he can possibly try his test using a different operating system (Linux machines, or VxWorks on the IOCs?) to try to identify the offending unit(s) (node vs switch)

Debbie and Diane are back to work on the Controller IOC. Nearly ready for Partha to begin mock-up/prototyping the Configuration Application.

Sergei will be developing a method to automatically generate the Feedback Control and Display EDM screens, using python and json

ACTION ITEMS:

Kukhee - try multicast testing with two groups defined

Diane, Partha, Debbie - start off the Configuration Application mock-up early next week