This page attempts to block out the noticeable episodes of computing and their priority and need for resource availability.
Instrument Related - Pre Launch
| What |
When |
Resource Uptime Needed |
| vibe/acoustic |
|
|
| TVAC |
Aug-Sept (40 days) |
up to 8 hr outages allowed |
Kennedy Ops |
|
|
ISOC testing - Pre-launch
| What |
When |
Resource Uptime Needed |
| ETE3 |
August 2007 (2 days) |
uptime needed |
| ETE4 |
Oct 2007 (2 days) |
uptime needed |
| ETE5 |
|
uptime needed |
| ETE6 |
|
uptime needed |
ISOC Ops Sim 1 |
Oct 2007 (about 4 days) |
uptime needed |
ISOC Ops Sim 2 |
Dec 2007 (about 4 days) |
uptime needed |
Flight Operations Post Launch
| What |
When |
Resource Uptime Needed |
First 2 weeks |
Feb |
"Guaranteed" up |
Next 6 weeks |
Through to end March |
|
Routine Ops |
April onwards |
up to 8 hrs; max 48 hrs |
Simulations
| What |
When |
Resource Uptime Needed |
| Preparations for 1 year run |
Several bursts of 1-3 farm-days, July-Aug |
Advance notice for up to a few days' outage |
| Backgrounds for 1 year run |
3 weeks in Sept |
Advance notice for < 1 day outage |
1 year run |
3 weeks in Oct |
Advance notice for < 1 day outage |
ISOC test datasets |
More bursts of 1-3 farm days, July-Sept |
Advance notice for up to a few days' outage |
Post ISOC test/pre launch datasets |
end Oct - Jan |
Advance notice for up to a few days' outage |
| |
|
|
| |
|
|