Item/TaskSub-item/taskOwnerDatesComment
FEB
 
Ben  
 layout 

Done 8/4

 
 fabrication 8/6-8/12 
 loading 8/13-8/20 
 testing 8/21- 
L4-6 Half-module production Tim  
 apv25 loading 8/7 
 hybrid & sensor QA 8/12 
 half-module production incl. QA 8/19-8/29When Tim is back.
L1-3 Module assembly Tim8/18-8/29 
 Modules for detector 8/18-8/29 
 Spares 9/1-9/5 
L4-6 Module assembly Tim8/18-8/29 
 Modules for detector 8/18-8/29 
 Spares 9/1-9/5 
FEB support Shawn  
 Machine slots in support box 8/8 
 Design pockets 8/21-8/29Need loaded FEB for design
 Fabrication and dry assembly 9/1-9/5 
Mechanical dry run assembly    
 w/o cabling and real FEBs (but FEB cold plate) 8/8 
     
Motion control system check Takashi8/15 
Survey   overview and procedures needed
 L1-3 module survey 9/1-9/5 
 L4-6 module survey 9/8-9/12 
 U-channels survey 9/8-9/12Need mounted modules (see below).
 SVT full assembly survey 9/22-9/26 
Internal cabling Tim/Dave  
 Magnet wire signal transmission test done 
 Magnet wire high voltage test 8/8Pelle will do it.
 FEB mezzanine card layout 8/8 
 FEB mezzanine card fabrication 8/15 
 Hybrid mezzanine card layout 8/13 
 Hybrid mezzanine card fabrication 8/20 
 L1-3 cross-over board design 8/18-8/22 
 L1-3 cross-over board layout 8/25-8/29 
 L1-3 cross-over board fabrication & assembly/checkout 9/1-9/10 
 pre-production bundle assembly 8/21-8/26 
 pre-production bundle test with FEB 8/27-9/3 
 production bundle assembly 9/4-9/12 
 FEB power bundle design (from flange) done 
 FEB power bundle assembly (from flange) 8/26Need cable length estimate. 2 days of shop work.
 FEB high voltage bundle design (from flange) done 
 FEB power bundle assembly (from flange) 8/26Need cable length estimate. 2 days of shop work.
External cabling & Power pelle  
 High voltage 8/222/3 bundles done. Waiting for more wire.
 Low voltage Done. 
 Fibers Done.Between flange and DAQ crate.
 PS checkout Done. 
 PS epics control 9/1Can control through backup interface until ready.
Power flange Pelle  
 Flange w/ board assembly 8/8One spare included.
 Testing with FEB and PS 8/8Need dummy connector on power. High voltage with banana plugs?
Signal flange Pelle  
 Board fabrication (5 boards) Done. 
 Board prepping 5/8-8/8 
 Board testing 8/18-8/19Needs Ben for high-speed tests.
 Flange w/ board assembly 8/20-8/27Potting.
 Board fabrication (spares) 8/20-8/27 
 Board loading (spares) 8/28-9/4 
 Board testing (spares) 9/5-9/6Needs Ben for high-speed tests
Chiller and cooling system Marco  
Target Clive/Marco  
 Design 8/6-8/15 
 Fabrication 8/18-8/22 
 Testing 8/25-8/26 
Wire frame holder Clive/Marco/Takashi  
 Design 8/6-8/15 
 Fabrication 8/18-8/22 
 Testing 8/25-8/26 
Mechanical dry run assembly  Shawn  
 U-supports, FEB cold plate, stages 8/8 
  Define cable lengths for power and HV bundles  8/8 
Motion control system check Takashi8/15 
Mechanical assembly    
 Mount modules in U-channels 9/1-9/5 
 Dress modules in U-channels with cabling 9/15-9/19 
 Assemble FEBs on cooling plate and dress with cables 9/15-9/19 
 Full SVT assembly including stages 9/15-9/19 
ATCA/RCE Platform hardware Ryan/Pelle  
 RTM layout 8/15After testing trigger interface at JLab.
 RTM fabrication & loading 8/18-9/1 
 RTM checkout 9/2-9/5 
SVT DAQ commissioning Ryan/Ben  
 Commissioning of RCE platform with multiple FEBs and hybrids 9/8-9/19Need: flanges, FEBs and hybrids. Can be done with spares if interfering with assembly.
 Commissioning/testing of full RCE platform 9/22-10/3Use all final hardware with increasing number of FEBs/modules.
Shipping Pelle/Matt  
 Box design 8/15Nr of boxes, isolator requirements for transport of delicate modules
 Procurement/fabrication 9/12 
 Assembly 9/19 