ATTENDEES
TOPICS:
Need to know-
1) the scope of the installation effort for each subsystem.
2) How much can be done without beam, before April turn-on
Current Plan for April Start-up
- April 1st - begin 2 weeks of PPS
- April 19th - beam on
- April 19 through May 5 - beam tune-up
- May 6 - Users start
Possible Alternate Plan
- April 19th through September no 120Hz user experiments, only up to 30Hz
- April 19th through September testing at 120Hz through TD11 only
add FCOM uplinks to
Switch |
IOCs for Feedback |
---|---|
swh-in20-nw02 |
in20-bp01, in20-bp02, in20-rf01 |
swh-li21-nw01 |
li21-bp01, li21-bp02, li21-bl01** |
swh-li24-nw01 |
li24-bp01, li24-bp02, li24-rf01, li24-bl01 |
swh-b136-nw01 |
bsy0-bp01 |
swh-b106-nw01 |
bsy0-bp02 |
swh-b105-nw01 |
ltu0-bp01, ltu1-bp01, ltu0-mg01? |
swh-b911-nw01 |
ltu1-bp02, ltu1-mg01? |
swh-b912-nw01 |
ltu1-bp03, ltu1-mg02? |
swh-b913-nw01 |
ltu1-bp04, und1-bp01, und1-bp02) |
swh-b921-nw01 |
und1-bp03, und1-bp04, dmp1-bp01 |
**- this new swh-li21-nw01 may be installed, move these iocs from swh-in20-nw02 to this switch
Network upgrade and test plan - to be done DURING downtime
- install all new fiber and new switches, leave old private switches in place for RF, BPMs, BLENs
- configure new switches for all BPMs, BLENs, RF eiocs
- THEN, for every IOC and EIOC involved in feedback, test the new network connections by making connection to new switch and ping
- this will likely take several days and will involve both Network group and each subsystem engineer (Kristi, Sonya, Sheng, Kuhkee)
- when done testing an IOC / EIOC move connections BACK TO ORIGINAL SETUP. We must leave the