You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 2 Next »

Item/TaskOwnersub-item/taskDatesComment
FEBBen
 
  
  layout

Done 8/4

 
  fabrication8/6-8/12 
  loading8/13-8/20 
  testing8/21- 
L4-6 Half-module productionTim   
  apv25 loading8/7 
  hybrid & sensor QA8/12 
  half-module production incl. QA8/19-8/29When Tim is back.
L1-3 Module assemblyTim   
L4-6 Module assemblyTim   
Mechanical dry run assemblyShawn   
  w/o cabling and real FEBs (but cold plate)8/8 
Motion control system checkTakashi 8/15 
SurveyTim/Takashi/John  overview and procedures needed
  Modules  
  U-channels  
  SVT full assembly survey  
Internal cablingTim/Dave   
  FEB mezzanine card layout8/8 
  FEB mezzanine card fabrication8/15 
  Hybrid mezzanine card layout8/13 
  Hybrid mezzanine card fabrication8/20 
  pre-production bundle fabrication8/21-8/26 
  pre-production bundle test with FEB8/27-9/3 
     
     
     
     

10. inner cables-- layout, assembly,  and test 11. meazzanine boards--layout, fab, load, test 12. target--design, fab, check 13. wires--design, fab, check 14. flange cards 15. outer power cables 16. Chiller and cooling system checkout 17. PS checkout 18. Shipping boxes

  • No labels