The MEC experiments scheduled for Run 24 (March 2025 - July 2025) are in non-standard configurations and (mostly) require significant work on motorization and its attendant parameter management. This confluence page will capture the precise control system requirements for each experiment and to create a proposed work plan for additional support external to the MEC team, e.g.f rom ECS Field Engineering. 

The following bullet points are extracted from notes of the 23 January 2025 ECS Priorization meeting between Peregrine McGehee and Eric Galtier.

  • 1008603 Hartley
    • water jet experiment
    • SPL at 2w, large optical spot
  • 1008454 Rocca
    • imaging on nanowires (MXI)
    • SPL at 2w, tight laser spot, exactly colinear to the FEL direction
  • 1008961 Czapla
    • imaging on Si samples (MXI) using a schlieren imaging technique
    • SPL at 1w, regular 45° tight focus
  • 1008968 Galtier
    • 2nd high resolution X-ray view, 2x MXI
    • SPL at 1w, regular 45° tight focus
  • 1008362 Ofori-Okai
    • THz using the SPL
    • SPL is split in 2, one for drive, one for THZ probe
  • 1008539 Nagler
    • LPL going upstream TCC, coupled to meV spectroscopy
  • summer shutdown possible outcome
    • start with maintenance and finish with SPL experiment to test TP