Time and Location

2pm Eastern time

Room F326 in F-wing at JLab

Agenda

Minutes

Present at JLab: Hovanes, Nerses, Krister, Stepan, F.X.

Present at SLAC: Sho, Takashi

  • Takashi described the HPS-specific applications requiring stepper motor control.
    • Target (new stage)
      • 2 foils and out position. May increase the number of foils to 5.
      • 2 limit switches, low precisions, ~100um, always use reset with limit switch on power loss
      • May need to put a wire on the stick for a harp scan after first chicane
    • Collimator (new stage)
      • 2 collimators and out position. May increase to 4.
      • adjustable 50um, need to monitor some rates to find optimal position. Can implement a scan also, 
      • adjustment will need to be redone every time the collimator is retracted.
      • Hovanes wanted to have specs of the stage (uni- and bi-directional reproducibility, accuracy, smallest increment)
    • SVT motion (2 new stages)
    • SVT scan (same stages as SVT motion)
    • There are other motor applications as well: 2C21, 2C24, 2CH00, beam blocker. Total 8 motors for HPS: 2 on space frame, 6 near beam dump alcove. 
  • Krister and Stepan discussed the magnet power supply controls
    • We will need the power supplies for: Moeller quads, Tagger magnet, minitorus, Pair spectrometer.
    • Krister pointed out that a lot of controls cabling, including magnet power supplies have been taken apart. Can be a major problem.
    • It might be easier to create new controls for some of them rather than to try to recreate what was there before.
    • Stepan and Krister will go into the hall to see what is still there.
  • No update on ECAL HV/LV, the motherboards is still being finalized.