Participants: 

LBNL: Katie Dunne, Timon Heim, Peilian Liu, Ben Nachman, Maurice Garcia Sciveres
SLAC: Nicole Hartman, Peter Kim, Martin Kocian, Rob Mina, Francesco Rubbo, Su Dong
ANL: Sergei Chekanov
KEK: Koji Nakamura 

Shift Schedule (tentative) 

DayShiftShifter
Thursday Sep/299am – 9pmSergei, Su Dong, Timon, Ben, Katie
Thursday – Friday9pm – 9amPeilian, Ben (->1am), Timon (->5am), Sergei (4am->)
Friday Sep/309am – 9pmSu Dong, Nicole, Sergei (->11am)
Friday – Saturday9pm – 9amTimon (->5am,10am->), Peilian, Rob (5am->)
Saturday Oct/19am – 9pmSu Dong, Rob(->10am), Ben (10am->), Timon(10am-2pm)
Saturday – Sunday9pm – 9amNo shift, LCLS at low energy. Ben and Su Dong switching cold->warm setup
Sunday Oct/2

9am – 9pm

Ben, Peter
Sunday – Monday9pm – 9amSu Dong, Nicole
Monday Oct/39am – 9pmFrancesco?/Martin?, Peter?
Monday – Tuesday9pm – 9amBen, Rob

Event Log

Sep/19-26 prep      

Sep/19: Previous dissembled Caladium is reassembled by Test Facility in the ESTB tunnel but parked on the side as beam pipe was reinstalled for a down stream experiment (somewhat of a surprise for us) this week. Caladium mover control electronics is still missing and to be installed next week. We checked the re-connections and found a few errors and missing links which got corrected. Connected the double chip module 94-04-03 as DUT with upgraded DUT CAT6 data cables and tried pixel digital calibration which worked as expected. Reordered the power supplies on the remote power strip to match the original panel in EPICS.     

Sep/20: Checking with Carsten about what is really going on this week, it turned out T-542 (sFlash) is taking the entire period Sep/22-Sep/26 so that the originally agreed Sep/26 for us has evaporated and we were never informed of that change. 

Sep/23: Checked with sFlash at ESA control room. The intense scene confirmed the fear that they will probably need the entire period, including Monday.

Sep/26: sFlash is continuing with their runs so that we are unlikely to have any chance to run for Monday, considering that Caladium still needs to be brought onto beam line after beam pipe removal. So Monday is expected to mainly doing lab test of the first RTI module to get proper configurations prepared and check other preparation items.   

Sep/27

Sep/28

Plan for today:

Activities:

Sep/29

Plan of the day:

Activities:

Sep 30