Minutes for SEECS/SLAC meeting July 20, 2011.

Bold face topics are to be addressed in the meeting.

Upcoming

Faisal is leaving SLAC next week, he will leave for Pakistan end of August.

Future & Publicity

Pakistani case study - Amber, Anjum

  1. 36 hosts are deployed so far and are aiming to deploy 60 hosts in total in Pakistan. As I understand it SEECS will be responsible for the hosts and their PingER app
  2. Another 5 monitoring nodes have been added in the month of July. 

Latest PERN network map

Anjum got latest PERN map. Notes from Anjum: The provided map is better than the existing one but its still not complete in information and not immediately useable for our purposes. HEC PERN topology maps have yet not been received.

Status of Pakistani PingER hosts

As updated on 7/20/2011.

Node

Status    

Comments

pinger.ustb.edu.pk

Down

Pinging by another IP, data not shown. Troubleshooting in progress.

monitor.niit.edu.pk

UP

IP changing.Troubleshooting in progress.

pingerqta.pern.edu.pk

Down

Not pingable, not accessible.Network issue.

pingerpwr.pern.edu.pk

UP

IP changing. Troubleshooting in progress.

pinger.giki.edu.pk

Down

Troubleshooting in progress.

Responsible people:

PingER managment

PingER traceroute archive site

PingER archive site - FYP (Ghulam, Farhan, Zafar)

Adding MOS and Alpha to pingtable.pl

TULIP

CBG TULIP Integration -- FYP (Bilal)

Best Line Approach CBG-TULIP (Zafar and Bilal)

First thing is the need of landmark sets and their RTT that can be fetched from a DB (They will be designing this DB).

Currently working on bestline approach. With bestline TULIP has 70% efficiency. Bestline will run before tiering and then reflex.cgi will be used.

Next Task is to enhance bestline.m so as to read data from table and use it for calculating geographical locations.

PerfSONAR (Pakistan)

PerfSONAR (USA)

  1. Zafar: Yee will meet Jason in person (at Joint Techs in Alaska in July) to tell him about SNMP-MA extensions. He thinks emailing is not a good idea. :P
  2. Zafar: Currently working on extending FTMA (which is a new PerfSONAR service and currently under developement) to add in support for MySQL.
  3. Faisal is fixing bugs with the new perfSonar mashup that Yee put up.

Possible projects

Future meeting time - Les

The next meeting is Wednesday, July 27th, 2011 (8 pm) for people in US and Thursday July 28st, 2011 (8 am) for people in Pakistan. Les is away the week after.