ATTENDEES

TOPICS:

Need to know-

1)      the scope of the installation effort for each subsystem.

2)      How much can be done without beam, before April turn-on

Current Plan for April Start-up

  • April 1st - begin 2 weeks of PPS
  • April 19th - beam on
  • April 19 through May 5 - beam tune-up
  • May 6 - Users start

Possible Alternate Plan

  • April 19th through September(question) no 120Hz user experiments, only up to 30Hz
  • April 19th through September testing at 120Hz through TD11 only

add FCOM uplinks to

Switch

IOCs for Feedback

swh-in20-nw02

in20-bp01, in20-bp02, in20-rf01

swh-li21-nw01(question) 

li21-bp01, li21-bp02, li21-bl01**

swh-li24-nw01     

li24-bp01, li24-bp02, li24-rf01, li24-bl01

swh-b136-nw01

bsy0-bp01

swh-b106-nw01

bsy0-bp02

swh-b105-nw01

ltu0-bp01, ltu1-bp01, ltu0-mg01?

  swh-b911-nw01

ltu1-bp02, ltu1-mg01?

swh-b912-nw01

ltu1-bp03, ltu1-mg02?

swh-b913-nw01

ltu1-bp04, und1-bp01, und1-bp02)

swh-b921-nw01 

und1-bp03, und1-bp04, dmp1-bp01

**- this new swh-li21-nw01 may be installed, move these iocs from swh-in20-nw02 to this switch

Network upgrade and test plan - to be done DURING downtime

  • install all new fiber and new switches, leave old private switches in place for RF, BPMs, BLENs
  • configure new switches for all BPMs, BLENs, RF eiocs
  • THEN, for every IOC and EIOC involved in feedback, test the new network connections by making connection to new switch and ping
    • this will likely take several days and will involve both Network group and each subsystem engineer (Kristi, Sonya, Sheng, Kuhkee)
    • when done testing an IOC / EIOC move connections BACK TO ORIGINAL SETUP. We must leave the