MD Priorities List
Priority | MD Item | Procedure Link | Machine Time (shifts) | Responsible Party | Needed By | Prerequisites | Notes |
---|---|---|---|---|---|---|---|
3 | Injector setup for 10deg off Schottky zero crossing | 3 | White | Maybe investigate smaller laser spot | |||
3 | Laser spot size variation | Discussion with Glen | |||||
3 | Linac Ballistic Data | 5 | |||||
3 | S20 Ballistic Data | Good pencil beam config | |||||
3 | Individual mechanical<>magnetic offsets in L2 | Loney | |||||
1 | S20 BBA | Oct 13, 2022 | 2 | Yocky | |||
2-4 | Notch Collimator recommissioning | 1+2 | Current energy spread may not be compatible with clean cuts | ||||
2 | S20 matching studies/emittance in S20 | Sep 29, 2022 | 1 | White | Good pencil beam config | ||
3 | 2nC running/instability investigation | 2 | Loney | FJD interested | |||
TBD | Two-bunch prep/setup | Yocky* | |||||
4 | BLEN sensitivities | BLEN Sensitivities MD | Alsberg | ||||
2 | Investigate orbit dependent matching into L2 | White* | BBA | FJD notes similar issue in LCLS–likely eta from BC1 | |||
1 | Complete ORM | Sep 15, 2022 | Loney | ||||
2 | Tuning IP with smaller beta* | Yocky | |||||
1 | Pencil beam config | Oct 13, 2022 | Alsberg | ||||
3 | Learning data for MDL FF / Track hardware issues | Sep 29, 2022 | Alsberg | ||||
4 | RF kicks | Alsberg | |||||
1 | Linac BBA | BBA Shift Plan | Loney | ||||
3 | Toroid ringing investigation | Sep 1, 2022 | Alsberg | ||||
4 | Injector RF Standby triggering | Loney | |||||
2 | Automated Steering development | White/all | |||||
2 | L1 orbit stability study | Oct 6, 2022 | Parker | ||||
2 | RF stability (jitter, jumps, and djrift) | Sep 15, 2022 | Ripman | ||||
2 | DC magnet stability | Sep 29, 2022 | Parker | ||||
2 | TCAV0 study (sigz v. Sch. phase, etc.) | Oct 6, 2022 | Parker | ||||
1 | Linac wakefield bump tuning exploration | Yocky | |||||
1 | Commissioning Laser Heater | Yocky* |