Schedule
Day shift: 9am–9pm / Night shift : 9pm–9am
Day/week | Date | Activities |
---|---|---|
Thursday | Nov/1 | Dismantling previous experiment. We might be able to get into ESA to prepare sometime in the afternoon. |
Friday | Nov/2 | Day: preparation / Night: first beam ~9pm |
Saturday | Nov/3 | Day: beam run / Night: MD, no beam to ESTB |
Sunday | Nov/4 | Full day ESTB beam |
Monday | Nov/5 | Full day ESTB beam |
Tuesday | Nov/6 | Full day ESTB beam |
Wednesday | Nov/7 | Day: ESTB beam until ~11pm end of period |
Preparation items:
1) Support table/platform behind Caladium to prop up the LBNL cosmic telescope of 1x1 foot cross section 3 feet long (with ~2 feet height adjustment).
2) Wireless boost in the tunnel: Juan from TestFac has been working on this and will ensure its installation.
3) Beam trigger availability: Will have 2-3 independently controllable beam triggers to work with (TTL or NIM). Will also add a NIM fanout in case needed. .
4) We ran short of remote CAM last time. Some more CAMs resurrected ?
5) Need to refresh/document procedure to operate the remote control of PSU->HV. Adding a couple of channels ?
Oct/30:
Schedule discussion with Carsten: Thursday 9am beam off to dismantle previous expt. SD will meet Carsten 10am at ESA to start process of moving Caladium back on beam line and decide how long a section of the beam pipe should be taken out (next experiment will need them reinstalled). Will also look for the support platform for LBNL cosmic telescope. Also confirmed we need the Wednesday day shift beam at the end.