Item/Task | Sub-item/task | Owner | Dates | Comment |
---|---|---|---|---|
FEB | Ben | |||
layout | Done | |||
fabrication | done | |||
loading | 8/29 | |||
testing 2 boards | 9/5 | |||
rest of FE boards fab and loaded | 9/12 | |||
all FE boards tested | 9/19 | |||
L4-6 Half-module production | Tim/Omar | |||
apv25 loading | done | |||
hybrid & sensor QA | done | |||
half-module production incl. QA | 9/5 | |||
L1-3 Module assembly | Tim/Sho | |||
Modules for detector | 9/5 | |||
Spares | 9/5 | |||
L4-6 Module assembly | Tim/Sho | |||
Modules for detector | 9/12 | |||
Spares | 9/12 | |||
FEB support | Richard | |||
Machine slots in support box | ||||
Design pockets (need final FE board) | ||||
Fabrication and dry assembly | 9/15 | |||
Mechanical dry run assembly | Who? | |||
w/o cabling and real FEBs (but FEB cold plate) | 9/5 | |||
Motion control system check | Takashi | |||
Test stages on vac box | 9/5 | |||
Connect bottom U channel, set limits, calibrate | 9/12 | conflict with survey? | ||
Connect top U channel, set limits, calibrate | 9/12 | |||
Survey | Tim/Sho | overview and procedures needed | ||
L1-3 module survey | 9/12 | |||
L4-6 module survey | 9/12 | |||
U-channels survey | 9/12 | Need mounted modules (see below). | ||
SVT full assembly survey | 9/22-9/26 | Coordinate with alignment group (see below) | ||
Internal cabling | Tim/Dave | |||
Magnet wire signal transmission test | done | |||
Magnet wire high voltage test | done | Pelle will do it. | ||
FEB mezzanine card layout | done | |||
FEB mezzanine card fabrication | 9/5 | |||
Hybrid mezzanine card layout | 9/5 | |||
Hybrid mezzanine card fabrication | 9/5 | |||
L1-3 cross-over board design | 9/12 | |||
L1-3 cross-over board layout | 9/12 | |||
L1-3 cross-over board fabrication & assembly/checkout | 9/12 | |||
LV mezzanine card layout | ||||
LV mezzanine card fabrication | ||||
HV mezzanine card layout | ||||
HV mezzanine card fabrication | ||||
pre-production bundle assembly | 9/12 | |||
pre-production bundle test with FEB | 9/19 | |||
production bundle assembly and test | 10/6 | critical path for full assembly (see below) | ||
FEB power bundle design (from flange) | done | |||
FEB power bundle assembly (from flange) | 8/26 | Need cable length estimate. 2 days of shop work. | ||
FEB high voltage bundle design (from flange) | done | |||
FEB power bundle assembly (from flange) | 8/26 | Need cable length estimate. 2 days of shop work. | ||
FEB data bundle design (to flange) | ||||
FEB data bundle assembly (to flange) | ||||
External cabling & Power | pelle | |||
High voltage | 8/22 | 2/3 bundles done. Waiting for more wire. | ||
Low voltage | Done. | |||
Fibers | Done. | Between flange and DAQ crate. | ||
PS checkout | Done. | |||
PS epics control | 9/5 | Can control through backup interface until ready. | ||
Power flange | Pelle | |||
Flange w/ board assembly | 9/12 | One spare included. | ||
Testing with FEB and PS | 9/12 | Need dummy connector on power. High voltage with banana plugs? | ||
Signal flange | Pelle | |||
Board fabrication (5 boards) | Done. | |||
Board prepping | Done. | |||
Board testing | Done. | Needs Ben for high-speed tests. | ||
Flange w/ board assembly | 8/20-8/27 | Potting. | ||
Board fabrication (spares) | 9/5 | |||
Board loading (spares) | 9/5 | |||
Board testing (spares) | 9/5 | Needs Ben for high-speed tests | ||
Chiller and cooling system | Marco | 9/12 | ||
Target | Clive/Marco | |||
Design | 9/5 | |||
Fabrication | 9/19 | |||
Testing | 9/26 | |||
Wire frame holder | Clive/Marco/Takashi | |||
Design | done | |||
Fabrication | 9/12 | Wire Stretching | ||
Testing | 9/12 | |||
U-supports, FEB cold plate, stages | 8/8 | |||
Define cable lengths for power and HV bundles | 8/8 | |||
Final SVT Assembly | ||||
Mount modules in U-channels | 9/22 | |||
Dress modules in U-channels with cabling | 9/26 | cabling not ready? | ||
Assemble FEBs on cooling plate and dress with cables | 10/17 | cables are ready 10/6 Need 11 days? | ||
Full SVT assembly including stages | 10/22 | Ready for full system | ||
ATCA/RCE Platform hardware | Ryan/Pelle | |||
RTM layout | done | After testing trigger interface at JLab. | ||
RTM fabrication & loading | done | |||
RTM checkout | 9/5 | |||
SVT DAQ commissioning | Ryan/Ben | |||
Commissioning of RCE platform with multiple FEBs and hybrids | 9/8-9/19 | Need: flanges, FEBs and hybrids. Can be done with spares if interfering with assembly. | ||
Commissioning/testing of full RCE platform | 10/20 | Use all final hardware with increasing number of FEBs/modules. | ||
Shipping | Pelle/Matt | |||
Box design | 8/29 | Nr of boxes, isolator requirements for transport of delicate modules | ||
Procurement/fabrication | 9/19 | |||
Assembly | 10/3 |