Item/TaskSub-item/taskOwnerDatesComment
FEB
 
Ben  
 layout 

Done 8/4

 
 fabrication 8/6-8/12 
 loading 8/13-8/20 
 testing 8/21- 
L4-6 Half-module production Tim  
 apv25 loading 8/7 
 hybrid & sensor QA 8/12 
 half-module production incl. QA 8/19-8/29When Tim is back.
L1-3 Module assembly Tim8/18-8/29 
 Modules for detector 8/18-8/29 
 Spares 9/1-9/5 
L4-6 Module assembly Tim8/18-8/29 
 Modules for detector 8/18-8/29 
 Spares 9/1-9/5 
Mechanical dry run assembly    
 w/o cabling and real FEBs (but cold plate) 8/8 
Motion control system check Takashi8/15 
Survey   overview and procedures needed
 Modules   
 U-channels   
 SVT full assembly survey   
Internal cabling Tim/Dave  
 Magnet wire signal transmission test done 
 Magnet wire high voltage test 8/8Pelle will do it.
 FEB mezzanine card layout 8/8 
 FEB mezzanine card fabrication 8/15 
 Hybrid mezzanine card layout 8/13 
 Hybrid mezzanine card fabrication 8/20 
 pre-production bundle assembly 8/21-8/26 
 pre-production bundle test with FEB 8/27-9/3 
 production bundle assembly 9/4-9/12 
 FEB power bundle design done 
 FEB power bundle assembly 8/26Need cable length estimate. 2 days of shop work.
 FEB high voltage bundle design done 
 FEB power bundle assembly 8/26Need cable length estimate. 2 days of shop work.
External cabling & Power pelle  
 High voltage 8/222/3 bundles done. Waiting for more wire.
 Low voltage Done. 
 PS checkout Done. 
 PS epics control 9/1Can control through backup interface until ready.
Power flange Pelle  
 Flange w/ board assembly 8/8One spare included.
 Testing with FEB and PS 8/8Need dummy connector on power. High voltage with banana plugs?
Signal flange Pelle  
 Board fabrication (5 boards) Done. 
 Board prepping 5/8-8/8 
 Board testing 8/18-8/19Needs Ben for high-speed tests.
 Flange w/ board assembly 8/20-8/27Potting.
 Board fabrication (spares) 8/20-8/27 
 Board loading (spares) 8/28-9/4 
 Board testing (spares) 9/5-9/6Needs Ben for high-speed tests
Chiller and cooling system Marco  
     
     
Target Clive/Marco  
 Design   
 Fabrication   
 Testing   
Shipping Pelle/Matt  
 Box design 8/12Nr of boxes, isolator requirements for transport of delicate modules
 Procurement/fabrication 9/12 
 Assembly 9/19 